AMB renovates Castelldefels and Gavà collector with an 8.8 million euro investment

The works, which will last until February 2028, will improve the reliability of the sanitation system and protect the Llobregat Delta.

Generic image of underground pipe renovation work in a coastal setting.
AI

Generic image of underground pipe renovation work in a coastal setting.

The Metropolitan Area of Barcelona (AMB) has started the renovation works of the interceptor collector that transports wastewater from Castelldefels and Les Botigues de Sitges to the Gavà-Viladecans wastewater treatment plant (EDAR).

The project, with a budget of 8.8 million euros funded by the Catalan Water Agency (ACA), began last August and is scheduled to finish in February 2028. The renovation of 3.6 kilometers of the pumping main will enhance the safety and reliability of the sanitation system, which has been in service for over three decades, and will reduce the risk of wastewater discharges into the environment, particularly in areas of environmental value and along the coast.
The system, operational since 1993, includes a pumping station adjacent to the UPC's Baix Llobregat Campus and a 6.17-kilometer collector. The complexity of the works lies in the need to keep the current collector operational without interruption while the new infrastructure is being built. Aigües de Barcelona, responsible for the execution, will need to plan the work with precision to ensure service continuity.
A significant portion of the new pipeline, approximately 1,200 meters, will run through the natural area of the Llobregat Delta, part of the Natura 2000 network. To minimize environmental impact, work on the Camí de la Pineda de Gavà will be carried out outside the nesting period (March-July 2027), and access to agricultural farms and the irrigation and drainage systems of the Parc Agrari del Baix Llobregat will be preserved.
The project involves the installation of 3,638 meters of new high-density polyethylene pumping main, with a diameter of 800 millimeters, along with 940 meters of auxiliary pipelines. It also includes six drainage manholes, seven aeration points, isolation valves, a flow meter, and a final load-breaking manhole.
Based on information from the official source: Àrea Metropolitana de Barcelona (AMB) - Sala de premsa (20/11/2026)