The interventions will take place in Sant Isidre, Planas, Santa Magdalena, and Llebeig streets, as well as in the alleys of Plaja street and Quarters street. The objective is to replace old and deteriorated pipe sections to reduce water leaks and improve the efficiency of the supply network, also renewing the isolation valves.
The work will be carried out progressively: from November 3rd to 10th in the alley connecting Quarters street with Plaça Major; from November 10th to 20th in Planas street; from November 20th to 27th in the dead-end alley of Plaja street; from November 27th to December 4th in Sant Isidre street; and from December 4th to 18th in Santa Magdalena and Llebeig streets.
During the execution of the works, there will be temporary traffic restrictions with limitations on vehicle passage, except for residents. Access to building entrances will be guaranteed, and outside working hours, the construction areas will be cordoned off. In the alley between Quarters street and Plaça Major, pedestrian passage will not be permitted during working days.